1 reviews | Active since Oct 2018
POOR SERVICE DELIVERY : MIDVAAL MUNICIPALITY : SIGNS OFF ON JOBS WITHOUT COMPLETING THE TASKS
The fuse on the transformer was struck by the storm on 15 January 2024. We reported it on 16 January 2024. We have had te resubmit the fault every day with no joy. We have contacted 5 individuals of whom 4 is technicians and nothing has been done. On 19 January 2024 a Eskom bakkie stopped at the pole after I contacted another individual and drove off seconds later. The premises is linked on 3 phase electricity but with the fuse down we only have 1 phase electricity. This results in not being able to pump water for the cattle and our tanks running low. We can't cook as we cant use the stove of big appliance. We are on 5 days without water and proper electricity. Eskom sogns the fault off as completed and doesn't make any attempts to assist. This is not the first time this happened and the previous time we had no electricity and water for 5 days as well. The messages now states it will only be attended to during normal working hours.